Mining Royalty Agreement in Turkey 2026

7 min read By Ozbek CPA Bu yazının Türkçesi

A mining royalty agreement lets a licence holder hand all or part of a site to a third party to operate, usually for a fee per tonne or a share of sales. Neither the licence nor the holder’s obligations to the authorities change hands. Below: the permission procedure, the single-agreement rule of 30 October 2025, liability and the 2026 tax burden.

Short answer

Under additional article 7 of Mining Law no. 3213 the agreement needs Ministry permission and is annotated on the mining register; activity without permission is halted. Underground coal is closed to all but public bodies. Labour and safety liability rests with the operator; the holder’s statutory duties continue.

Permissioncondition for the agreement to work
One per sitethe rule since 30 October 2025
20 percentvalue added tax on leasing a right
0.948 percentstamp duty on a contract stating a sum

What the agreement is

Mining rights in Turkey go only to citizens and to locally incorporated companies whose constitution permits mining. An investor therefore has two routes to a site: buy the company that holds the licence, or enter into a royalty agreement with the holder. On the second route the licence stays put while production and its risk pass to the operator. The contract is treated as a produce lease, since the fee follows output rather than a fixed rent.

What counts as a royalty agreement

  • The licence holder stays the same; the site is handed over
  • The fee follows tonnage produced or sales proceeds
  • Commercial risk of production sits with the operator
  • Permission required; contract annotated on the register

What does not count

  • Transfer of the whole licence, which is registered
  • A mining services contract paid at a fixed rate
  • A site the holder works with its own employees
  • A plain lease of machinery or equipment

Permission and registration

Article 101 of the Mining Regulation sets out the procedure. The General Directorate is not a party to the contract; it checks the parties and the site, then annotates the agreement.

  1. The contract is drawn up. Coordinates, term and end date, including any extension the parties expect to seek.
  2. The licence holder clears its dues. Licence fees, stamp duty and the environmental guarantee paid; no overdue state royalty.
  3. The operator files its documents. Shareholding, addresses, registered electronic mail address, financial capacity and bank details.
  4. The General Directorate assesses. Whether the area is large enough to mine and whether operations would interfere with one another.
  5. Permission is granted and the contract annotated. Later extensions or coordinate changes are fresh applications.
Legal capacityArticle 6eligibility to hold a mining right

A company files its shareholders, addresses and registered electronic mail address; its constitution must cover mining.

Financial capacity30 percentminimum equity share for a company

The balance is shown by bank documents. An individual shows the full amount by a bank reference letter under fifteen days old.

Technical staffSupervisorrequired on a permitted site

No permission is granted on a site with an operating permit until a resident supervisor is appointed.

What happens without permission

Activity under an unpermitted agreement is halted. The contract may bind the parties, but nothing can be produced on the site.

Where it cannot be used

SituationRule
Underground coal operationNot available except to public bodies and their affiliates
Second agreement on one siteNot available outside group IV (c) and public licences
Contract with no coordinatesNot annotated on the mining register
Same area at a different levelNo separate agreement allowed
Extension or change of coordinatesCounts as a fresh application
Share transfer in the operatorPermission needed above ten percent

The single-agreement rule is new. Until 30 October 2025 several agreements could be made within one site if the areas did not overlap. That has been reversed: outside group IV (c) licences, covering metallic minerals, and public licences, one agreement per licence area is the limit. Check the licence group before planning to work a site in parcels.

Where liability stays

ObligationRests with
Labour law, health and safetyOperator
Production, dispatch and stock recordsOperator
Technical duties under the Mining LawLicence holder
State royalty and licence feesLicence holder
Environmental guarantee, rehabilitationLicence holder
Register filings and permission requestsLicence holder

The first row is the one argued over. Where the licence holder keeps its own supervisor or technical staff on site, social security practice and the courts may treat it as principal employer and the operator as subcontractor, with joint liability for wage claims and unpaid premiums. The Court of Cassation describes the arrangement as a time-limited lease of operating rights.

The tax burden

TaxHow it applies in 2026
Value added taxLeasing a right is taxable, at 20 percent
Who declares itThe operator, where the holder is not registered
Income tax withholding20 percent on payments to an individual
Corporate taxOrdinary income of a corporate licence holder
Stamp duty0.948 percent, or 0.189 percent if treated as rent
Stamp duty ceiling29,115,961.10 lira

The common mistake is to assume the property rental exemption carries over. It does not: it reaches only immovable property outside a business, and a mining right is a right. Where the holder is not registered and the operator is, the operator accounts for the tax itself under full withholding. Income tax withholding arises only where the holder is an individual. For stamp duty the rate turns on how the contract is characterised and the base on the minimum production commitment; a written ruling before signature settles the point.

Step oneThe operator paysThe fee and the value added tax on it go to the licence holder.
Step twoThe holder declaresIt books the fee as revenue and declares the taxes that fall on it.
Step threeState royalty is paidThe holder owes it; the cost can be passed on by contract.
Recharged public costs

State royalty, licence fees and easement charges are the holder’s debt to the authorities. The burden can be shifted by contract, but the documents are in the holder’s name, so the operator cannot deduct directly; a recharge invoice from the holder restores the deduction.

What the contract has to cover

  1. Area and termCoordinates, levels and end dateWorking levels, plant and stockpile areas defined, with a consequence for working outside them.
  2. FeeMeasurement and adjustment rulesWeighing point, moisture and grade adjustment; for a revenue share, returns, discounts and freight.
  3. OutputMinimum production commitmentShortfall and force majeure; the commitment also fixes the stamp duty base.
  4. Public duesExit on non-paymentCollection from the guarantee, termination and recourse if state royalty goes unpaid.
  5. SecurityLayered guaranteesBank guarantee, cash deposit, insurance and liquidated damages; recourse for accidents.
  6. ExitHandover and closureRemoval of stock, waste rock and equipment, rehabilitation, workforce and final notification.

The mistakes made most often

  • Starting production before permission. A signed contract is not enough; the activity is halted.
  • Not checking the licence group. Splitting a site among operators is blocked on most groups.
  • Overlooking value added tax. The property rental exemption does not reach the leasing of a right.
  • Ignoring the employer question. The holder’s own staff on site opens the principal employer argument.

Frequently asked questions

Does the agreement have to be notarised?

No. The law asks for Ministry permission and an annotation on the register; a notary helps on evidence but produces no effect without permission.

Can a foreign-owned company be the operator?

A licence goes only to companies incorporated in Turkey, so the investor sets up a local company first, which can act as operator if it meets the capacity tests.

Can two operators work the same licence area?

As a rule no. Since 30 October 2025 one agreement per licence area is the limit, except on group IV (c) metallic mineral licences and public licences.

Who answers for a workplace accident?

Administrative, financial and legal liability rests with the operator. The holder’s statutory duties continue, and its own staff on site opens the principal employer argument.

What happens when the term ends?

It is struck from the register. An extension is a fresh application, so producing before it is granted and annotated risks being treated as unpermitted activity.

Ozbek CPA works on the permission file for mining royalty agreements, fee and measurement clauses, the value added tax and stamp duty burden, and recharged public costs. A related subject is tax treaties in Turkey. To have a contract reviewed, get in touch.

Sources
  • Mining Law no. 3213 — additional article 7 and articles 2, 6, 14 and 38
  • Mining Regulation, article 101 on royalty arrangements
  • Regulation amending the Mining Regulation — Official Gazette of 30 October 2025, no. 33062
  • Income Tax Law no. 193, article 70 and article 94/5-a
  • Value Added Tax Law no. 3065, articles 1/3-f and 17/4-d, and the leasing section of the general application communique
  • Stamp Duty Law no. 488 and general communique series no. 71 — Official Gazette of 31 December 2025, no. 33124, fifth repeated issue
  • General Directorate of Mining and Petroleum Affairs — current application documents and announcements

This article provides general information and does not replace advice on your specific situation. Rules, rates and thresholds change, so please contact us before acting on it.

Contact Information

Reach out to us!

Let’s Talk

Our vision emphasizes collaboration and growth, aligning with your business goals.

    Contact Us






    Your message has been sent successfully!